wiz-icon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

4 men can complete a piece of work in 2 days. 4 women can complete the same piece of work in 4 days whereas 5 children can complete the same piece of work in 4 days. If 2 men, 4 women and 10 children work together, in how many days can the work be completed?

A
1 day
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B
3 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
2 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
4 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
E
None of these
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is A 1 day
1 man can do the work in 8 days.
1 woman can do the work in 16 days.
1 child can do the work in 20 days.
2m + 4w + 10c can do the work in -
(28+416+1020)×d = 1
(14+14+12)×d = 1
d = 1

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Speed-Distance-Time
QUANTITATIVE APTITUDE
Watch in App
Join BYJU'S Learning Program
CrossIcon