A man and a boy working together can complete a work in 24 days, if for the last 6 days, the man alone does the work, then it is completed in 26 days, How long will the boy to complete the work alone ?

A
72 Days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B
20 Days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
24 Days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
36 Days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is A 72 Days
Let 1 man's 1 days' work = 1x and 1 boy's 1 days' work = 1y Then 1x+1y=124
Also given 20x+20y+6x=1 20(1x+1y)+6x=120(124)+6x=1
6x=1566x=16x=36 1y=124136=3272=172y=72
The boy will take 72 days to complete the work alone

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Time and Work
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon